HS2’s twin tunnels towards Euston have reached their halfway point, with 2.25 miles of each 4.5-mile bore excavated beneath London, although passenger services into the terminus remain years beyond the planned completion of tunnel construction.
The two tunnelling machines, Karen and Madeleine, have been working non-stop from their launch point at Old Oak Common, advancing towards Euston at 16 metres a day. Tunnel construction is due to finish in 2027.
The scale of the work is substantial: the tunnels, each about 7.55 metres in diameter, are expected to generate around 1.5 million tonnes of excavated material and require nearly 50,000 concrete segments.
For passengers, however, completion of this engineering work is distinct from the opening of the railway. High-speed services between Old Oak Common and Birmingham are expected to begin between 2036 and 2039. The Birmingham–Euston connection is not expected to follow until between 2040 and 2043. The project has suffered repeated delays, largely because of funding concerns.
Rail minister Lord Hendy described the milestone as an important step towards bringing HS2 into central London. He said the railway would provide greater capacity and faster journeys, alongside long-term benefits for growth, jobs and homes.
HS2 Ltd chief executive Mark Wild praised the teams building the programme’s last deep-bored tunnel, describing their work as fundamental to the ambition of increasing prosperity around Euston.
Wild said a comprehensive reset of the programme was in its final stages, with the aim of delivering the railway safely at the lowest reasonable cost. He said the new line would complement the existing Euston station and West Coast Main Line, adding capacity for fast, reliable long-distance journeys. The tunnelling milestone marks physical progress; the wider programme’s cost and delivery timetable remain the larger test.