£50m M49 junction could open before structural repairs are finished

Temporary restrictions and safety monitoring are being considered at the M49 junction, where embankment defects have added to years of delays.

A £50 million motorway junction near Bristol could open under temporary restrictions before repairs to structural defects are completed, seven years after it was built.

The M49 junction, described as “Britain’s most expensive dead end”, was completed in late 2019 to connect a distribution park with the motorway. It has never opened to traffic.

Highways England said this week that technical advisers were examining whether restrictions or additional safety monitoring could allow an earlier opening while the remaining work is completed. No decision has been made, and a further update is expected in the new year.

The junction’s two-bridge roundabout was intended to keep heavy goods vehicles out of nearby villages and ease congestion on routes including the A403. Businesses using the distribution park include Amazon, Tesco, Lidl, Next, DHL and The Range. The scheme was also intended to support the economy around Avonmouth and Severnside.

Instead, motorists who inadvertently drive towards the junction reach a dead end.

The initial delays concerned land ownership and responsibility for paying for a connection to the local road network. South Gloucestershire Council previously said those issues had been resolved and that it hoped the junction would open by the end of this year.

The council took on construction of the link road after earlier plans involving developers fell through. But structural defects found in the junction’s embankments earlier this year created another obstacle.

A highways spokesperson said: “Our specialist technical advisers are exploring all possible options to identify the safest and quickest way forward.”

The spokesperson added: “Safety remains our absolute priority. Any option will only be taken forward if our experts are confident that it can be operated safely.”

Local councillor Simon Johnson welcomed the possibility of a restricted opening, while expressing frustration at the delay.

“Local residents relied on National Highways to build this motorway junction and give them their village back,” he said.

“It’s incredibly frustrating that after six years it’s still not able to open fully.”

Johnson suggested traffic lights and monitoring vehicle numbers could help make a limited opening possible while full repairs were awaited. He urged National Highways to establish whether that could be done and inform residents and businesses as soon as possible.

For now, both a permanent repair solution and the possibility of opening sooner remain under examination.